Section 38 Agreement & New Road Adoption

We handle everything from technical approval through to Certificate 3 – including the backlog defects that are stopping your scheme from completing. Fixed-fee resolution, expert adoption management, capital released.

Expert Section 38 management for developers, main contractors, and housing schemes requiring adoption certainty

You’ve built the roads. Now you need them adopted so you can release bonds, complete final sales phases, and move capital to your next project.

But you’re 18 months past practical completion with a defect list that keeps growing, a highway authority asking for yet another round of remedials, and final sales plots sitting empty because buyers can’t get mortgages on unadopted roads.

Unlock adoption and release retained capital

You need Certificate 3 issued, bonds released, and schemes signed off. Not more delays whilst you chase the original contractor or argue about who’s responsible for drainage issues discovered two years after handover.

We deliver this across the South West, South Wales, and the Thames Valley – managing Section 38 agreements from initial technical approval through to final adoption, or stepping in to resolve backlog schemes where defects are preventing sign-off.

What we can deliver for your site...

Why Section 38 schemes stall, and what it costs you

Every month your adoption stays incomplete costs you money.

Stalled adoptions are more than just an administrative nuisance; they are a drain on your balance sheet. With over £1.1 billion in developer contributions currently sitting unspent in local authority accounts, the system is clogged.

If you are facing 6-12 month delays, you are likely dealing with:

There's a proven way to unlock these schemes...

Schemes adopted, bonds released, capital back working for you. We specialise in fixing what's preventing sign-off

Fixed-fee defect resolution:

We quote a fixed price for resolving your entire defect list and getting Certificate 3 issued. You know your costs upfront, not endless variations and excuses.

One partner for all trades:

Surfacing, drainage, lighting, signage, line marking, landscaping. You're not coordinating six different subcontractors who all blame each other.

Fast turnaround on backlog schemes:

Most defect resolution completed within 12-16 weeks of instruction. Certificate 3 typically issued 8-12 weeks after completion, not years.

Authority liaison handled:

We manage all correspondence, inspections, re-inspections with highway authorities. You're informed, not doing the work.

Documentation sorted:

As-builts, CCTV surveys, testing certificates, health and safety files, commuted sum calculations. Everything required for Certificate 3 delivered to specification.

Bond release progression:

Clear route through Certificate 1, 2, 3 with bond releases at each stage. Your capital comes back progressively, not locked up until the very end.

The Google logo is displayed above five gold stars in a row, representing a five-star rating for commercial car park surfacing or a high review score. | Highways Plus

Why developers and contractors choose Highways Plus

You’re managing multiple schemes, tight cash flow, and boards asking why capital’s still tied up in projects that finished 18 months ago. You need a partner who understands that adoption isn’t a construction challenge – it’s a commercial problem affecting your ROI.

What sets us apart

Schemes stuck for two, three, five years with defect lists no one would touch. We step in, price it, fix it, get Certificate 3 issued.

One price for getting your scheme adopted, including all defects, all trades, all documentation. No variations unless you change scope.

Twenty-five years managing Section 38 agreements means we know exactly what each authority requires, how inspections work, what documentation passes first time.

We’re certified to the National Highway Sector Schemes standards highway authorities require. ISO 9001, 14001, 45001 quality assurance means work’s done right first time.

Need junction works on existing highways alongside your estate roads? We handle both adoption processes as one integrated project.

Drainage adoption often runs parallel to highway adoption. We coordinate both, ensuring surface water systems meet current standards and get adopted alongside roads.

A clear, structured process that keeps your scheme progressing

Section 38 adoption requires methodical progression through three certificates, each with specific requirements, inspections, and documentation. Careful management at each stage prevents delays and ensures bond releases proceed.

What you get...

Most schemes follow staged delivery – technical approval and agreement formation first, construction with hold-point inspections, then systematic progression through the three-certificate process.

For new schemes: technical approval typically 8-12 weeks, construction timelines vary by size, maintenance period 12 months minimum. For backlog schemes: defect assessment 2-3 weeks, resolution works 12-16 weeks, Certificate 3 typically 8-12 weeks after completion.

1.

Technical submission and agreement formation:

Design review against authority standards, submission preparation with all required drawings and calculations, bond and commuted sum negotiation. Agreement executed, you're ready to build to adoptable standards.

2.

Construction with staged inspections:

Hold-point inspections at base course, drainage installation, kerbing, surface course stages. Issues identified early, not discovered at final inspection two years later.

3.

Certificate 1 (Provisional Completion):

Base layers, drainage, kerbing, lighting installed and inspected. Up to 50% bond released, 12-month maintenance period starts, buildings can be occupied but roads remain your maintenance responsibility.

4.

Certificate 2 (Surface Course Completion):

Final wearing course laid and inspected, remedial works from maintenance period completed. Additional 20-30% bond released, extended maintenance period continues.

5.

Certificate 3 (Final Adoption):

All conditions satisfied - as-builts submitted with CCTV drainage surveys, health and safety files delivered, commuted sums paid, Section 104 adoption confirmed if required. Roads adopted, final bond released, your obligations end.

Section 38 agreement CASE STUDY

Residential development, 47 plots, Somerset - backlog scheme

A magnifying glass icon focuses on a warning triangle with an exclamation mark inside, set against a bright green circular background—ideal for highlighting commercial car park surfacing alerts. | Highways Plus

The Challenge:

Icon of a person wearing a hard hat and suit next to a cog, symbolising engineering, technical work, or commercial car park surfacing project management, on a bright green circular background. | Highways Plus

Our Solution:

A dark green bullseye target with an arrow in the centre, set against a bright lime green circular background—ideal for highlighting precision in commercial car park surfacing. | Highways Plus

The Outcome:

Proven delivery of Section 38 adoption across diverse sectors

Whether you’re developing residential schemes, commercial estates, or mixed-use projects, you need confidence that roads will meet adoptable standards and achieve adoption sign-off without years of defect negotiations.

Sectors that rely on us:

Housing schemes requiring Section 38 adoption for estate roads. Backlog defect resolution on partially completed schemes, or full adoption management from technical approval through Certificate 3.

Business parks, retail developments, industrial estates where adopted access roads affect property values and mortgage availability. Adoption certainty supporting commercial exit strategies.

Tier 2 and regional contractors requiring specialist adoption expertise they don’t maintain in-house. Reliable subcontractor for Section 38 compliance and certification progression.

Complex schemes requiring coordinated Section 38 (internal roads), Section 278 (junction works), and Section 104 (drainage) adoption. Single partner managing all three processes.

Council-led housing developments and regeneration schemes requiring adoption-standard construction. Public sector procurement experience with full compliance documentation.

Affordable and mixed-tenure schemes where adoption affects residents’ service charges and property values. Fixed-fee certainty supporting development appraisals.

Your Section 38 agreement questions, answered...

For new schemes: technical approval 8-12 weeks, construction timeline varies by scheme size, Certificate 1 issued at substantial completion, 12-month maintenance period minimum, Certificate 3 typically 6-12 months after Certificate 2 depending on authority processing times. Total timeline: 18-36 months from agreement formation. For backlog schemes we’re resolving defects on: assessment 2-3 weeks, works 12-16 weeks, Certificate 3 typically 8-12 weeks after completion.

Fixed-fee service for schemes stalled at adoption due to outstanding defects. We take over your defect list, price all remedial works across all trades as a single package, complete the works, manage authority re-inspections, and deliver Certificate 3. You get one quote, one invoice, one partner accountable for getting the scheme adopted.

Costs vary significantly by scheme size and complexity. Highway authority fees typically include technical approval fees, inspection fees, and bond administration charges. You’ll also need performance bond (usually 110% of construction value) and commuted sums for ongoing maintenance of non-standard features. For backlog defect resolution, we provide fixed-fee quotes based on your specific defect list. All pricing transparent at quotation stage.

Yes, this is exactly what our Backlog Defect Resolution service addresses. We’ve rescued dozens of schemes where original contractors liquidated, refused to return, or disappeared. We assess current condition against adoption requirements, price outstanding works, and take full responsibility for getting Certificate 3 issued.

We manage both. Most residential developments require Section 38 for internal estate roads plus Section 278 for junction improvements on existing highways. We coordinate both adoption processes, manage the different approval routes, and ensure both achieve sign-off. One partner, integrated delivery.

Highway authorities typically require confirmation of Section 104 drainage adoption (or formal agreement from the water company) before issuing Certificate 3. We coordinate both adoption processes, ensuring surface water systems meet water company standards whilst integrating with highway drainage. Where SuDS features are involved, we manage Lead Local Flood Authority approval alongside highway authority sign-off.

As-built drawings in CAD showing all highway features and utility diversions, CCTV drainage surveys for all gullies and sewers with defect reports, street lighting testing certificates and photometric surveys, health and safety files per CDM regulations, asset records using authority-specified templates, commuted sum calculations for non-standard features, confirmation of Section 104 adoption where required. Everything required for Certificate 3 submission prepared to each authority’s specific requirements.

Yes. Many backlog schemes have residents paying £500-£1,500 annually for private road maintenance that should’ve ended with adoption. We’ve helped dozens of schemes achieve adoption so management companies can be dissolved and maintenance responsibility transfers to the highway authority. Residents immediately benefit from zero ongoing fees.

Initial defect assessment: within one week of instruction. Site meeting with highway authority: typically within two weeks. Fixed-fee quotation provided: 2-3 weeks after assessment. Works mobilisation: typically 3-4 weeks after instruction to proceed, subject to authority inspection availability.

Book a Free, No-Obligation Section 38 Assessment
Book a Free, No-Obligation Section 38 Assessment

Stuck with a scheme that won't adopt or planning a new development requiring Section 38?

Book a Free, No-Obligation Section 38 agreement Assessment

We’ll review your scheme, assess adoption requirements, identify any barriers to Certificate 3 issuance, and provide a written report with fixed-fee quotation for resolution or adoption management.

No obligation, no sales pressure – just expert advice from specialists w

Call or fill out our form and we'll be in touch within 24 hours.

Highway adoption and agreements

Latest surfacing and civil's advice and news

Ready to discuss your project?

Complete the form below to speak to a specialist about your requirements or call us on 01761 202 012

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.